DCC: Latest Scala rebuild progress news

Home 5 News 5 DCC: Latest Scala rebuild progress news

The following work within the Scala Cinema in Prestatyn is now complete:

  • The seating now installed in both auditoriums
  • Hand over from RL Davies (the contractor) to Denbighshire County Council took place on Monday the 22nd of September 2008
  • The lighting rig in the second auditorium has been installed
  • Acoustic panels in both auditoriums have been fitted
  • The stage installation has been completed and the cinema installation will be ongoing through to the end of October with a view to testing and commissioning.
  • The ticketing counter will be installed by the 31st of October
  • Newman Online have successfully tendered for the ticketing system
  • Colours within the building include orange, red, brown, grey, black, vivid green and yellow!

Source: Denbighshire County Council Press Release 01.10.08